Pipeline and trench work for Feldmoching railway crossing, pipe jacking under DB tracks
Original notice title
SV-JWA-260603-003 - TW - Feldmoching Bahnquerung, Rohr-/Tiefbauarbeit FW + Pressung unter DB-Gleisen
Opportunity Score
Why this score?
Opportunity
50 / 100
Complexity
75 / 100
Risk factors
Work under active railway tracks with strict vibration and deformation limits; groundwater management; coordination of...
No disclosed budget or estimated value; may be lower than expected or subject to negotiation.
Deep Portfolio Analysis
Uses:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications
Overview
Moderate opportunityKey Facts
- Works contract
- 2 lots
- Duration until Apr 2027
- Construction of district heating pipelines (KMR) in Munich-Feldmoching to connect two network areas.
- Northern crossing: approx. 215m in DN80 (supply/return) pipes.
Show full summary
This negotiated procedure (without call for competition) under the EU Utilities Directive covers construction works for new district heating pipeline crossings under two railway lines in Munich-Feldmoching. The work includes deep excavation, microtunneling under active railway tracks, and installation of district heating pipes. The tender is divided into two lots: northern crossing (Lot 1) and southern crossing (Lot 2). The award is based solely on price (100%). The deadline for participation requests is 2026-07-09 at 13:00 local time. No estimated value is provided. The tender is open to SMEs and requires electronic submission via SWM's supplier portal. Only the structured notice and XML notice were analyzed; full procurement documents were not available.
Risks
Work under active railway tracks with strict vibration and deformation limits; groundwater management; coordination of...
No disclosed budget or estimated value; may be lower than expected or subject to negotiation.
Analysis may be incomplete
Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.
Key Requirements
Technical
- Tenders must be in German (DEU).
Administrative
- Electronic submission via SWM supplier portal required; written submissions excluded.
- Submission deadline: 2026-07-09 at 13:00 local time (participation requests).
Requirements may be incomplete.
Award Criteria
Lot 1
Lot 2
Buyer
Name
SWM Infrastruktur GmbH & Co. KG
Location
München, DEU
Website
Identifier
DE 813 865 922
Lots (2)
LOT-0001
SV-JWA-260603-003 - TW - Feldmoching Bahnquerung, Rohr-/Tiefbauarbeit FW + Pressung unter DB-Gleisen
Northern railway crossing (Bahnquerung Nord). Approximately 215m of DN80 (supply/return) pipes, microtunneling under DB tracks with steel concrete protective pipes DN500 (approx. 46m each), including shafts, manholes, and associated works.
Location
Duration
Category
Selection criteria
Deadline
Award details
Additional CPV codes
Show original TED data
Original TED description
Bahnquerung Nord
LOT-0002
SV-JWA-260603-003 - TW - Feldmoching Bahnquerung, Rohr-/Tiefbauarbeit FW + Pressung unter DB-Gleisen
Southern railway crossing (Bahnquerung Süd). Approximately 300m of DN150 (supply/return) pipes, microtunneling under DB tracks with steel concrete protective pipes DN600 (approx. 69m each), including shafts, manholes, and associated works.
Location
Duration
Category
Selection criteria
Deadline
Award details
Additional CPV codes
Show original TED data
Original TED description
Bahnquerung Süd
Procurement Details
- Publication date
- 08 Jun 2026
- Notice type
- Contract notice — standard
- Languages
- German
Reference metadata
- Notice subtype
- 17
- Notice version
- 1
- Legal basis
- 32014L0025
Reference IDs
- Tender ID
- 393153-2026
- Source notice ID
- fbf928b8-5aac-4651-a44a-ffc10b03adff
Documents (1)
Similar tenders
Poland – Building construction work – "Modernizacja Centrum Przedsiębiorczości w Starachowicach" w ramach tytułu inwestycyjnego „AkTYwne Miasto. Razem dla rozwoju Starachowic”
Poland – Construction work – Zaprojektowanie i wykonanie robót dla zadania pn.: "Prace na linii kolejowej C–E 20 na odcinku Pilawa - Łuków"
Poland – Construction work – Zaprojektowanie i wybudowanie linii kolejowej dużych prędkości od Węzła CPK (bez Węzła CPK) do Węzła Bolimowskiego (bez Węzła Bolimowskiego)
Germany – Construction work – Rohbau- u. Tiefbauarbeiten Promenadenschule Jülich
Germany – Underground work other than tunnels, shafts and subways – 2. BA Regenwassergrundleitungssystem
Poland – Construction work for buildings relating to various means of transport – Przebudowa i rozbudowa dworca autobusowego w Mielcu w celu przystosowania go do pełnienia roli węzła przesiadkowego
Opportunity Score
Why this score?
Opportunity
50 / 100
Complexity
75 / 100
Risk factors
Work under active railway tracks with strict vibration and deformation limits; groundwater management; coordination of...
No disclosed budget or estimated value; may be lower than expected or subject to negotiation.
Deep Portfolio Analysis
Uses:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications